pm-claude-skills/exports/chatgpt/pm-operations/project-status-report/SYSTEM_PROMPT.md
T
Claude 572b8acf8c Add multi-platform export generator (single source of truth)
Make the library multi-platform without duplicating content. Each
skills/<name>/SKILL.md body remains the single source of truth; a new
generator renders platform-ready exports from it.

- scripts/build-exports.mjs — dependency-free Node generator with a PLATFORMS
  registry so new platforms (Gemini, Cursor, …) are a few lines. Ships ChatGPT
  exports at exports/chatgpt/<bundle>/<skill>/SYSTEM_PROMPT.md (172 skills),
  plus generated index READMEs. Supports --platform and --check.
- exports/ — generated ChatGPT system prompts, ready to paste into a Custom GPT.
- .github/workflows/check-generated.yml — fails a PR if exports or
  web/skills.json drift from the source skills.
- README "Works With" now documents the ready-to-use exports and regen command.
- CHANGELOG + SKILL-AUTHORING-STANDARD note the generated artifacts.

Co-Authored-By: Claude Opus 4.8 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_016JWn5jRD5tcEFKrubjQ6Px
2026-06-17 08:01:20 +00:00

3.4 KiB

Project Status Report Skill

Produces a clear, structured project status report — the weekly communication that keeps stakeholders informed without requiring a meeting.

Required Inputs

  • Project name
  • Reporting period
  • Current RAG status (Red / Amber / Green)
  • Key milestones (due, delivered, coming)
  • Issues or blockers
  • Decisions needed from stakeholders
  • Budget status (if tracked)
  • Audience (steering committee / sponsor / PMO / full team)

Output Structure


Project Status Report: [Project Name]

Period: [Date range] | Author: [PM] | Next report: [Date]


Overall Status

Dimension Status Last period Trend
Overall Red / Amber / Green [Last] Improving / Stable / Declining
Schedule
Budget
Scope
Risks

RAG definitions:

  • Green: On track. No significant issues.
  • Amber: At risk. Issues identified but mitigations in place.
  • Red: Off track. Escalation or decisions required to recover.

Executive Summary

[3-5 sentences. Headline story. If it is Red, say so immediately and why. Never bury bad news after good news.]


Milestone Progress

Milestone Due date Status Comment
[Milestone] [Date] Complete / At risk / Delayed / On track [One line]

Completed this period: [What was delivered] Due next period: [What is expected]


Issues and Blockers

[Issue title] — Critical / High / Low

  • Description: [What the issue is]
  • Impact: [What happens if unresolved]
  • Owner: [Who is resolving]
  • Action: [What is being done]
  • Resolution date: [When it will be closed]

Risks

Risk Likelihood Impact Mitigation Owner
[Risk] H/M/L H/M/L [Action] [Name]

Decisions Required

Decision Background Options Recommendation Needed by
[Decision] [Context] [Options] [Recommendation] [Date]

Budget Summary

Budget Actual to date Forecast Variance
Total £ £ £ £ F/A

Next Period Plan

[3-5 specific bullet points — what will happen next period]

Writing Rules

  • Never soften a Red status
  • Milestones are binary: complete or not complete
  • Decisions must be genuinely actionable
  • Keep to one page where possible

Quality Checks

  • Red status is stated immediately (not buried after positives)
  • Every issue has a named owner and a resolution date
  • Decisions required are genuinely actionable by the audience
  • Milestones are binary (complete or not complete — no "85% done")
  • Executive summary can stand alone for a stakeholder who reads nothing else

Anti-Patterns

  • Do not rate project health as Green while listing unresolved critical blockers
  • Do not report milestone progress as a percentage — milestones are binary: complete or not complete
  • Do not bury risks at the bottom — if something is high risk, it belongs in the executive summary
  • Do not leave decisions required without specifying who must decide and by when
  • Do not write an executive summary that requires reading the full report to understand — it must stand alone

Example Trigger Phrases

  • "Write a project status report for [project]"
  • "Generate a RAG status update for [project]"
  • "Write the steering committee report for [project]"