Files
pm-claude-skills/skills/risk-register/SKILL.md
T
mohitagw15856 ae6ea4d53e feat: v12.0.0 — 150-skill milestone, 15 new skills across 10 bundles
Adds 15 new skills reaching the 150-skill milestone:

Data & Analytics (pm-data):
- cohort-analysis: retention curves, LTV projection, behavioural segmentation, SQL reference queries
- data-pipeline-spec: ETL/ELT design with SLAs, DQ rules, error handling, compliance

Customer Success (pm-cs):
- renewal-playbook: health snapshot, value story, commercial scenarios, objection responses, 16-week timeline
- customer-success-plan: joint success plan with milestones, mutual commitments, escalation path

People & Leadership (pm-people):
- 360-feedback-template: survey instrument + narrative report with strengths and development themes
- team-health-check: Spotify-model assessment across 7 dimensions with facilitation guide

Operations (pm-operations):
- risk-register: L×I scoring, RAG heat map, mitigation and contingency plans
- raci-matrix: role definitions, decision map, anti-pattern guide, communication template

Marketing & GTM (pm-gtm):
- social-media-strategy: audience profile, content pillars, KPIs, 4-week starter calendar
- product-positioning-doc: April Dunford-style positioning, messaging hierarchy, persona messaging

Discovery (pm-discovery):
- customer-journey-map: stage-by-stage journey with touchpoints, emotions, and prioritised opportunities

Delivery (pm-delivery):
- user-story-writer: Given/When/Then ACs, edge cases, definition of done, epic decomposition

Advanced (pm-advanced):
- ai-ethics-review: fairness, bias, transparency, privacy, safety, accountability, societal impact

Sales (pm-sales):
- partnership-proposal: mutual value, commercial model, joint GTM plan, governance

Design (pm-design):
- design-system-audit: component coverage, token consistency, WCAG, adoption, remediation roadmap

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
2026-05-26 21:58:13 +01:00

212 lines
9.0 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
---
name: risk-register
description: "Build and maintain a project or product risk register. Use when asked to create a risk register, identify project risks, build a risk matrix, or document risks and mitigations for a programme. Produces a complete risk register with likelihood/impact scoring, RAG status, ownership, and prioritised mitigations."
---
# Risk Register Skill
This skill produces a complete risk register for a project, programme, or product. Output follows standard risk management practice with likelihood × impact scoring, RAG status, a risk heat map, and specific mitigation and contingency plans. Ready to share with a project board, steering committee, or programme office.
## Required Inputs
Ask the user for these if not provided:
- **Project or product name**
- **Project stage** (discovery / delivery / launch / live / programme-level)
- **Key objectives** — what is the project trying to achieve?
- **Known risks** — anything already on the team's radar (even informal concerns count)
- **Key dependencies** — external vendors, teams, systems, or regulatory approvals
- **Deadline or milestone sensitivity** — are there hard dates that cannot move?
- **Audience** — who will read this? (internal team / executive steering / external board / regulator)
## Output Structure
---
# Risk Register: [Project / Product Name]
**Project stage:** [Discovery / Delivery / Launch / Live / Programme]
**Version:** [1.0]
**Owner:** [PM / Programme Manager / Risk Lead]
**Last reviewed:** [Date]
**Next review:** [Date — recommend weekly during delivery, monthly during discovery]
**Status:** [Active / Archived]
---
## 1. Risk Scoring Framework
**Likelihood (L)**
| Score | Label | Definition |
|---|---|---|
| 5 | Almost certain | >80% probability of occurring |
| 4 | Likely | 6080% probability |
| 3 | Possible | 4060% probability |
| 2 | Unlikely | 2040% probability |
| 1 | Rare | <20% probability |
**Impact (I)**
| Score | Label | Definition |
|---|---|---|
| 5 | Critical | Programme failure, regulatory breach, major financial loss, safety event |
| 4 | High | Significant schedule delay (>4 weeks), scope reduction, reputational damage |
| 3 | Medium | Moderate delay (14 weeks), cost overrun, reduced quality |
| 2 | Low | Minor delay (<1 week), manageable cost increase |
| 1 | Negligible | Minimal impact, easily absorbed |
**Risk Score = L × I**
| Score | RAG | Action |
|---|---|---|
| 2025 | 🔴 Critical | Immediate escalation; active management required |
| 1219 | 🔴 High | Owner-assigned mitigation; weekly review |
| 811 | 🟡 Medium | Mitigation planned; fortnightly review |
| 47 | 🟡 Low | Monitor; monthly review |
| 13 | 🟢 Negligible | Accept; review if context changes |
---
## 2. Risk Register
| ID | Risk | Category | L | I | Score | RAG | Owner | Status | Mitigation | Contingency | Review date |
|---|---|---|---|---|---|---|---|---|---|---|---|
| R01 | [Risk description — be specific: "Third-party API may not support required volume, causing X to fail"] | [Schedule / Technical / Resource / Commercial / Compliance / External] | [15] | [15] | [L×I] | 🔴/🟡/🟢 | [Name] | [Open / Mitigating / Closed] | [What are we doing to reduce likelihood or impact?] | [What do we do if it happens?] | [Date] |
| R02 | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] |
---
## 3. Risk Categories — Common Risks by Type
Use these to prompt risk identification. Add, remove, or customise for your project.
### Schedule & Delivery
- Key milestone depends on a dependency that has not confirmed availability
- Team capacity reduced by planned or unplanned absence during critical period
- Technical complexity is underestimated — story points consistently overrun
- External approval (regulator, legal, procurement) takes longer than planned
### Technical
- Integration with a third-party system not yet prototyped or agreed
- Existing technical debt makes the change harder or riskier than estimated
- Security or compliance review required before launch has not been scoped
- Performance under production load untested
- Key technical knowledge held by one person (single point of failure)
### Resource & People
- Key SME or engineer leaving or unavailable during critical phase
- Budget not confirmed for Phase 2 of the project
- Stakeholder sponsor changes role or leaves the organisation
- Team not yet at full capacity (hiring lag, access issues, onboarding time)
### Commercial & Financial
- Vendor or partner contract not yet signed
- Cost estimate based on assumptions that have not been validated
- Revenue or savings case depends on assumptions outside the team's control
- Currency exposure or exchange rate risk for international projects
### Compliance & Regulatory
- Data privacy impact assessment (DPIA) not yet complete
- Regulatory approval required and timeline is uncertain
- GDPR, HIPAA, SOC 2, or sector-specific compliance requirement not yet mapped
- Legal review of terms of service or contracts pending
### Stakeholder & Adoption
- Key user group has low awareness or motivation to adopt the change
- Internal resistance from a team that will be affected by the change
- Executive sponsor not consistently engaged — decisions are slow
- Communications plan not yet agreed with change management team
### External
- Market or competitive change could undermine the business case
- Macroeconomic conditions affect budget or priority
- Supplier or infrastructure provider risk (e.g. cloud provider, hardware)
- Geopolitical or regulatory environment change
---
## 4. Risk Heat Map
Plot risks by likelihood (Y axis) and impact (X axis):
```
│ Low Medium High Critical
│ (1) (2-3) (4) (5)
─────────┼────────────────────────────────────
Almost │ 🟡 🟡 🔴 🔴
certain │
(5) │
─────────┼────────────────────────────────────
Likely │ 🟡 🟡 🔴 🔴
(4) │
─────────┼────────────────────────────────────
Possible │ 🟢 🟡 🟡 🔴
(3) │
─────────┼────────────────────────────────────
Unlikely │ 🟢 🟢 🟡 🟡
(2) │
─────────┼────────────────────────────────────
Rare │ 🟢 🟢 🟢 🟡
(1) │
```
[Plot each risk ID on this grid — e.g. R01 lands at L4/I5 = 🔴 Critical]
---
## 5. Top Risks — Executive Summary
For steering committee or board-level reporting:
| Rank | Risk | Score | RAG | Owner | Mitigation status |
|---|---|---|---|---|---|
| 1 | [Most critical risk — plain English description] | [X] | 🔴 | [Owner] | [Active / Planned / Not started] |
| 2 | [...] | [...] | 🔴 | [...] | [...] |
| 3 | [...] | [...] | 🟡 | [...] | [...] |
| 4 | [...] | [...] | 🟡 | [...] | [...] |
| 5 | [...] | [...] | 🟡 | [...] | [...] |
**Decisions required from steering:**
- [Any risk that requires budget, scope, or timeline decision to mitigate]
---
## 6. Risk Changes Since Last Review
| Risk ID | Change | Detail |
|---|---|---|
| [R03] | Score increased | [L moved from 2 → 4 — vendor confirmed delay in API availability] |
| [R07] | Risk closed | [Legal sign-off received on 12 May] |
| [NEW] | New risk identified | [R09 — budget freeze announcement affects Phase 2 funding] |
---
## 7. Risk Closure Criteria
A risk is closed when:
- The risk event can no longer occur (e.g. milestone passed, contract signed), OR
- The residual risk score drops to Negligible (13) AND the team formally accepts it, OR
- The risk has materialised and transitioned to an **issue** (tracked separately)
**Issues log:** [Link to issues log — risks that have materialised and are now active problems being managed]
---
## Quality Checks
- [ ] Every risk has a specific owner — not "the team" or "TBD"
- [ ] Mitigations describe what is actively being done — not "monitor and review"
- [ ] Contingency plans exist for all Critical and High risks
- [ ] Risk descriptions are specific — "vendor may be late" is not specific enough; name the vendor and the dependency
- [ ] Register has been reviewed in the last [X] days
- [ ] Closed risks are archived, not deleted — they provide audit trail
- [ ] Risks are distinguished from issues — a risk is something that might happen; an issue is something that has happened
## Example Trigger Phrases
- "Build a risk register for our product launch"
- "Create a risk matrix for [project name]"
- "What risks should I document for a data migration project?"
- "Generate a risk register for our steering committee"
- "Help me identify and score risks for our Q3 delivery plan"