   port to other agents and chat LLMs as system prompts).

2. Python helper scripts (stdlib-only) for the three strongest skills:
   - sprint-planning: capacity_calculator.py (recommended commitment)
   - rice-prioritisation: rice_calculator.py (ranks, flags quick wins/moonshots)
   - cs-health-scorecard: health_score.py (weighted total + RAG)
   Each is wired into its SKILL.md and synced to the plugin copies.

3. Explicit skill tiering — TIERS.md + README section marking 46
   Production-Ready skills and calling out Experimental (external-dependency)
   ones; everything else is Stable.

4. Repository hygiene — new CHANGELOG.md (Keep a Changelog format) and
   SKILL-AUTHORING-STANDARD.md; refreshed SECURITY.md version table and
   helper-script disclosure; added .gitignore.

5. Related Projects — README section linking to alirezarezvani/claude-skills
   and the major awesome-claude-skills / awesome-claude-code lists.

Co-Authored-By: Claude Opus 4.8 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_016JWn5jRD5tcEFKrubjQ6Px
2026-06-17 07:48:48 +00:00

122 lines
5.3 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
---
name: sprint-planning
description: "Structure and facilitate sprint planning sessions. Use when asked to plan a sprint, organise backlog items, assign story points, create sprint goals, or prepare sprint planning agendas. Produces a sprint goal, velocity-calibrated backlog, capacity plan, risk flags, and a structured sprint planning meeting agenda."
---
# Sprint Planning Skill
Transform raw backlog items into a structured, achievable sprint with clear goals, velocity-calibrated scope, and team-ready output.
## What This Skill Produces
- **Sprint Goal** — single, outcome-focused sentence the whole team can rally around
- **Sprint Backlog** — prioritised list of user stories with story point estimates and acceptance criteria
- **Capacity Plan** — team availability breakdown accounting for holidays, meetings, and focus time
- **Sprint Planning Agenda** — structured 2-hour meeting agenda with timings
- **Risk Flags** — blockers or dependencies that could derail the sprint
## Required Inputs
Ask for (if not already provided):
- Sprint duration (1 or 2 weeks)
- Team size and velocity (average story points per sprint)
- Top 35 backlog items or epics to pull from
- Any known absences, holidays, or team events
- Previous sprint's incomplete items (carry-overs)
## Sprint Goal Formula
Use this structure:
> "This sprint we will [deliver X outcome] so that [user/business benefit], measured by [success indicator]."
Never write sprint goals as task lists. Always outcome-first.
## Story Point Calibration
| Complexity | Points | Description |
|---|---|---|
| Trivial | 1 | Clearly understood, no unknowns |
| Small | 2 | Straightforward, minor effort |
| Medium | 3 | Some complexity, clear path |
| Large | 5 | Complex, needs design or research |
| Very Large | 8 | High uncertainty, may need splitting |
| Epic | 13+ | Too large — must be split before sprint |
Flag any item estimated at 8+ and recommend splitting.
## Capacity Formula
```
Available capacity = (Team size × Sprint days × Focus hours/day) × Availability factor
Focus hours/day: 6 (accounting for meetings, Slack, admin)
Availability factor: 0.70.85 depending on holidays/events
Story points to commit = Historical velocity × Availability factor
```
## Programmatic Helper
This skill ships with a stdlib-only Python script that computes capacity instead of estimating it by hand. Use it whenever the team's numbers are known — it applies the availability and 80% commit-ratio rules consistently.
```bash
# Quick estimate from flags
python3 scripts/capacity_calculator.py --team 5 --days 10 --velocity 30 --availability 0.8 --carryover 5
# Detailed estimate from per-member availability (JSON via stdin or --input file.json)
echo '{"sprint_days":10,"historical_velocity":40,"carryover_points":8,
"members":[{"name":"Ada","available_days":10},{"name":"Linus","available_days":7}]}' \
| python3 scripts/capacity_calculator.py --input -
```
The script returns available focus hours, a velocity figure adjusted for real availability, the **recommended commitment** (capped at 80% of velocity), and the remaining **capacity for new work** after carry-overs. Run it first, then build the sprint backlog to fit the recommended number. Add `--json` to pipe the result into other tooling.
## Output Format
### Sprint [N] — [Start Date] to [End Date]
**Sprint Goal:**
> [Goal statement]
**Team Capacity:** [X] story points available (based on [Y] team members, [Z]% availability)
**Sprint Backlog:**
| Priority | Story | Points | Owner | Acceptance Criteria |
|---|---|---|---|---|
| 1 | [Story title] | [N] | [Team member] | [When X then Y] |
**Carry-Overs from Previous Sprint:**
- [Item] — Reason for carry-over: [brief explanation]
**Risks & Dependencies:**
- [Risk description] → Mitigation: [action]
**Sprint Planning Agenda:**
- 00:0000:10 — Review sprint goal and team capacity
- 00:1000:40 — Walk through backlog items, confirm estimates
- 00:4001:20 — Assign stories, identify dependencies
- 01:2001:50 — Review acceptance criteria per story
- 01:5002:00 — Confirm sprint commitment and close
## Guidelines
- Always challenge stories missing acceptance criteria — flag them explicitly
- Recommend the team commits to 80% of available capacity, not 100%
- If no velocity data is provided, assume 2030 points for a 5-person team as a starting point
- Highlight any story with unclear ownership as a blocker
## Quality Checks
- [ ] Sprint goal is outcome-focused (not "implement X" — something like "users can do Y")
- [ ] Team capacity is calculated using actual availability, not theoretical 100%
- [ ] Every story has an acceptance criterion (flag any that don't)
- [ ] Stories estimated at 8+ points are flagged for splitting
- [ ] Carry-overs from last sprint are accounted for in capacity
## Anti-Patterns
- [ ] Do not write sprint goals as task lists — goals must be outcome-focused and scoreable pass/fail at sprint end
- [ ] Do not commit to 100% of available capacity — always recommend 80% to preserve slack for unplanned work
- [ ] Do not carry stories with no acceptance criteria into the sprint — flag them as blockers before committing
- [ ] Do not allow stories estimated at 8+ points into the sprint without splitting them first
- [ ] Do not ignore carry-over items when calculating capacity — they consume capacity and must be accounted for before new work is pulled in