- Added templates/pm-sprint-agent/ directory with full agent template - AGENT.md system prompt with explicit step-by-step workflow - 2 subagents: capacity-analyst and risk-scorer - 2 connectors: linear and jira (with example configs) - Symlinked skills from main library: sprint-planning, sprint-brief - orchestrate.sh end-to-end workflow script - examples/ folder with input and output examples - tests/ folder with smoke test - Updated README to position skills as building blocks for agent templates - Added Anthropic agent templates announcement reference (May 5, 2026) - Bumped marketplace.json to v8.0.0 - Listed 7 candidate agent templates this library supports This is the first agent template in the library. More to follow.
205 lines
7.8 KiB
Markdown
205 lines
7.8 KiB
Markdown
# Sprint 23 Plan
|
|
|
|
**Sprint Goal:** Reduce checkout abandonment by 20%
|
|
**Duration:** 2 weeks
|
|
**Team Size:** 5 engineers
|
|
**Generated:** 2026-05-05 14:30 BST
|
|
**Connector Used:** linear
|
|
|
|
---
|
|
|
|
## Capacity Summary
|
|
|
|
### Headline numbers
|
|
|
|
| Metric | Value |
|
|
|---|---|
|
|
| Base capacity | 130 story points |
|
|
| Capacity hits | -16 story points |
|
|
| Buffer reserved (20%) | -22 story points |
|
|
| **Available capacity** | **92 story points** |
|
|
|
|
### Per-engineer breakdown
|
|
|
|
| Engineer | Available SP | Notes |
|
|
|---|---|---|
|
|
| Engineer 1 (Sarah) | 22 | Full availability |
|
|
| Engineer 2 (Marcus) | 18 | 2 days PTO mid-sprint |
|
|
| Engineer 3 (Priya) | 22 | Full availability |
|
|
| Engineer 4 (David) | 12 | On-call week 1 (50% reduction) |
|
|
| Engineer 5 (Lin) | 18 | 2 days at conference week 2 |
|
|
|
|
### Assumptions used
|
|
- Baseline velocity: 13 points/engineer/week (calibrated from last 3 sprints: 12.8, 13.2, 13.0 average)
|
|
- Buffer applied: 20%
|
|
- Capacity hits: 4 PTO days, 5 on-call days, 2 conference days
|
|
|
|
### Confidence: **High**
|
|
Historical velocity provided and capacity hits are confirmed in the team calendar.
|
|
|
|
### Caveats
|
|
- Unplanned production incidents could reduce on-call engineer's capacity further
|
|
- New starter onboarding could pull from more senior engineers' time
|
|
- Sprint review prep (~4 hours team-wide) is included in the buffer
|
|
|
|
---
|
|
|
|
## Sprint Plan
|
|
|
|
### Selected items (87 of 92 available story points)
|
|
|
|
| Issue | Title | SP | Priority | Owner |
|
|
|---|---|---|---|---|
|
|
| CHK-142 | Add saved-cart recovery email at 30 min | 8 | High | Sarah |
|
|
| CHK-138 | Fix slow-loading payment iframe on Safari | 5 | High | Marcus |
|
|
| CHK-156 | A/B test: simplified checkout vs current | 13 | High | Priya |
|
|
| CHK-149 | Add address auto-complete for international | 8 | Medium | Sarah |
|
|
| CHK-161 | Show estimated delivery date earlier in flow | 5 | Medium | Marcus |
|
|
| CHK-145 | Improve guest checkout conversion | 13 | High | Priya |
|
|
| CHK-167 | Reduce required fields on payment step | 5 | High | David |
|
|
| CHK-152 | Optimise checkout JS bundle size | 8 | Medium | Lin |
|
|
| CHK-159 | Better error messages on card decline | 3 | High | David |
|
|
| CHK-163 | Track funnel drop-off in analytics dashboard | 5 | Medium | Sarah |
|
|
| CHK-171 | Bug fix: discount code validation race condition | 5 | High | Lin |
|
|
| CHK-175 | Bug fix: tax calculation off by 1 cent in EU | 3 | Medium | Marcus |
|
|
| CHK-177 | Bug fix: Apple Pay button not appearing on iOS 17 | 6 | High | David |
|
|
|
|
**Total: 87 story points** (5 points unallocated as additional buffer)
|
|
|
|
### Definition of done
|
|
|
|
- All A/B test variants are deployed behind feature flags
|
|
- Analytics events fire correctly for funnel tracking
|
|
- All bug fixes have regression tests
|
|
- Cross-browser testing complete (Chrome, Safari, Firefox, Edge)
|
|
- Mobile testing complete (iOS, Android)
|
|
- Performance budget met (no checkout step exceeds 2.5s LCP)
|
|
- Team retro signed off by sprint owner
|
|
|
|
### Dependencies flagged
|
|
|
|
- CHK-156 depends on the analytics events from CHK-163 being deployed first
|
|
- CHK-145 may require design review for any new UI elements
|
|
- CHK-177 requires testing on physical iOS 17 devices
|
|
|
|
---
|
|
|
|
## Risk Assessment
|
|
|
|
### Overall sprint risk: **Medium**
|
|
|
|
The plan is realistic but has some concentration risk on Priya (two of the larger items).
|
|
|
|
### Risk score breakdown
|
|
|
|
| Dimension | Average score (1-5) | Highest-risk items |
|
|
|---|---|---|
|
|
| Size risk | 2.4 | CHK-156, CHK-145 (both 13 points) |
|
|
| Dependency risk | 2.0 | CHK-156 (depends on CHK-163) |
|
|
| Knowledge risk | 2.6 | CHK-156, CHK-145 (both Priya only) |
|
|
|
|
### Per-item risk scores (top 5)
|
|
|
|
| Item | Size | Dep | Know | Composite | Flags |
|
|
|---|---|---|---|---|---|
|
|
| CHK-156 (A/B test) | 4 | 3 | 4 | 3.7 | Large + dependency + Priya only |
|
|
| CHK-145 (guest checkout) | 4 | 1 | 4 | 3.0 | Large + Priya only |
|
|
| CHK-177 (Apple Pay) | 3 | 2 | 3 | 2.7 | iOS 17 testing required |
|
|
| CHK-152 (JS bundle) | 3 | 1 | 3 | 2.3 | Lin only knows the build system |
|
|
| CHK-167 (required fields) | 2 | 2 | 2 | 2.0 | Frontend + backend coordination |
|
|
|
|
### Risk patterns identified
|
|
|
|
**Single-engineer concentration**
|
|
- Items affected: CHK-156, CHK-145, CHK-149, CHK-163 (all Priya/Sarah)
|
|
- Why this is risky: 39 of 87 story points (45%) depend on two engineers
|
|
- Suggested mitigation: Pair Priya with Marcus on CHK-156 to spread knowledge
|
|
|
|
**Bug-fix load (within acceptable range)**
|
|
- Items affected: CHK-171, CHK-175, CHK-177 (14 SP total)
|
|
- Why this is acceptable: 16% of capacity, below the 30% threshold
|
|
|
|
### Pre-sprint mitigation actions
|
|
|
|
1. **Pair Priya with Marcus on CHK-156** — Sarah Chen — by sprint kickoff
|
|
2. **Confirm iOS 17 device availability for CHK-177** — David Park — by EOD Monday
|
|
3. **Get design review scheduled for CHK-145** — Sarah Chen — by EOD Tuesday
|
|
4. **Verify analytics dashboard has capacity for new events (CHK-163)** — Lin Wang — by sprint kickoff
|
|
|
|
### Items recommended for breakdown
|
|
|
|
- **CHK-156 (A/B test: simplified checkout)** — at 13 points and high knowledge concentration, recommend breaking into:
|
|
- CHK-156a: Build A/B variant of checkout flow (8 SP)
|
|
- CHK-156b: Wire up analytics tracking for the test (5 SP)
|
|
|
|
---
|
|
|
|
## Kickoff Brief
|
|
|
|
### Sprint at a glance
|
|
|
|
**Goal:** Reduce checkout abandonment by 20%
|
|
|
|
This sprint is laser-focused on conversion optimisation across the checkout funnel. We're shipping the most impactful changes our funnel analysis identified: saved-cart recovery, simplified checkout flow (A/B tested), better error handling, and improving guest checkout conversion.
|
|
|
|
We'll know we succeeded if checkout completion rate increases by 4 percentage points (current 82% → target 86%).
|
|
|
|
### Why this sprint matters
|
|
|
|
Checkout abandonment is currently costing us approximately £180k per month in lost revenue. The funnel analysis from Q1 identified seven specific friction points — six of those are addressed in this sprint. The seventh (international currency display) is being deferred to next sprint pending design.
|
|
|
|
### What's being shipped
|
|
|
|
**Conversion optimisation (61 SP)**
|
|
- Saved-cart recovery email
|
|
- A/B test of simplified checkout
|
|
- Better guest checkout
|
|
- Address auto-complete
|
|
- Earlier delivery date display
|
|
- Reduced required fields
|
|
|
|
**Performance and analytics (13 SP)**
|
|
- Checkout JS bundle optimisation
|
|
- Funnel drop-off tracking
|
|
|
|
**Bug fixes (14 SP)**
|
|
- Safari payment iframe slowness
|
|
- Discount code race condition
|
|
- EU tax calculation
|
|
- Apple Pay on iOS 17
|
|
- Card decline error messages
|
|
|
|
### What we're NOT doing this sprint
|
|
|
|
- International currency display (deferred — needs design)
|
|
- Mobile checkout redesign (deferred — out of sprint scope)
|
|
- New payment method integration (deferred — Q3 priority)
|
|
|
|
### Definition of success
|
|
|
|
- Checkout completion rate ≥ 86% (measured 30 days post-deploy)
|
|
- A/B test reaches statistical significance within 14 days
|
|
- All bug fixes deploy without regression
|
|
- No production incidents from changes shipped this sprint
|
|
|
|
### Risks the team should know
|
|
|
|
- Two of our highest-impact items depend heavily on Priya — we've paired her with Marcus to spread knowledge
|
|
- CHK-156 should be broken into two smaller items at refinement
|
|
- iOS 17 device availability needs confirmation before sprint start
|
|
|
|
---
|
|
|
|
## Action Items for Sprint Planning Meeting
|
|
|
|
1. ✋ **Review the risk assessment** with the team — discuss the single-engineer concentration on Priya
|
|
2. ✋ **Decide whether to break down CHK-156** into two smaller items
|
|
3. ✋ **Confirm iOS 17 device availability** with David before locking in CHK-177
|
|
4. ✋ **Confirm capacity assumptions** match what engineers actually expect
|
|
5. ✋ **Lock in the sprint goal** — get verbal commitment from the team
|
|
6. ✋ **Update Linear** with the agreed sprint scope after the meeting
|
|
|
|
---
|
|
|
|